Optimum lot size "WI" - Least unit cost procedure

$
0
0

Three groups of Lot-sizing procedures are available:

 

  • Static lot-sizing procedures
  • Period lot-sizing procedures
  • Optimum lot-sizing procedures

 

I will explain here about one of the Optimum lot-sizing procedures: Least unit cost procedure (WI).

 

Feature

Starting from the shortage date, successive requirements are grouped together to form lots until total costs per unit reach a minumum level. The total cost are equal to the sum of the lot size independent costs plus the total storage costs.

 

Prerequisite

- Lot size field (MRP 1 view) is set with WI for Least unit cost procedure.

- Lot size independent costs (MRP 1 view) and storage costs indicator (MRP 1 view) is set.

  Ordering costs is 100 in this sample.

1-21-2015 1-17-26 PM.png

   Storage costs percentage for storage cost indicator 1 of plant 1000 is 10% in this sample. It is maintained in customizing OMI4.

1-22-2015 12-44-01 PM.png

- Price is set. It depends on price control. If price control is V, the price is "Moving price"; if price control is S, the price is "Standard price".

  Price is 20 in this sample.

1-21-2015 1-20-09 PM.png

- Requirements exist. In this sample, there are 4 planned independent requirements (PIRs). They are with date 2015/2/6, 2015/2/13, 2015/2/20 and 2015/2/27.

1-21-2015 1-33-38 PM.png

 

Calculation Logic

 

Calculation result of this sample.

Requirement DateRequirement qtyLot SizeLot Size Ind. CostStorage CostTotal CostUnit Cost
          2015/2/6          1000     1000          100               0          100     0.100
          2015/2/13          1000     2000        38.36     138.36     0.069
          2015/2/20          1000     3000        76.71     215.07     0.072
          2015/2/27          1000     4000      115.07     330.14

     0.083


Since the Unit cost for Lot Size 2000 is minimum, requirements are grouped together to form lots with qty 2000.

1-21-2015 2-00-25 PM.png

Formula

 

- Lot size = current Lot Size + new requirement qty.

- Storage Cost = ( Requirement * Price * Storage Cost  Percentage * Time in shortage ) / ( 100 * 365)

- Total Cost = current Total Cost + Newly calculated Storage Cost

- Unit Cost = Total Cost / Lot Size

 

Explaination

 

On 2015/2/6, shortage occurs.

            Time in shortage is 0 days.

            Storage cost = 0.

            Total cost = storage cost 0 + Lot size ind. cost 100 = 100

            Unit cost = Total cost 100 / Lot size 1000 = 0.100

 

On 2015/2/13

            Time in shortage is 7 days.

            Storage cost = (requirement qty 1000 * price 20 * percentage 10 * Time in shortage 7 ) / (100 * 365) = 38.36

            Total cost = storage cost 38.36 + current total cost 100 = 138.36

            Unit cost = Total cost 138.36 / Lot size 2000 = 0.069

 

On 2015/2/20

            Time in shortage is 14 days.

            Storage cost = (requirement qty 1000 * price 20 * percentage 10 * Time in shortage 14 ) / (100 * 365) = 76.71

            Total cost = storage cost 76.71 + current total cost 138.36 = 215.07

            Unit cost = Total cost 215.07 / Lot size 3000 = 0.072

 

On 2015/2/27

            Time in shortage is 21 days.

            Storage cost = (requirement qty 100 * price 20 * percentage 10 * Time in shortage 21 ) / (100 * 365) = 115.07

            Total cost = strorage cost 115.07 + current total cost 215.07 = 330.14

            Unit cost = Total cost 330.14 / Lot size 4000 = 0.083

 

Source Code

See attached text file.